The construction of the 154 kV Substation section has been completed - Solar Farm-1
07.05.2020
Customer
DTEKThe construction of the 154 kV Substation section has been completed - Solar Farm-1, which provides power output to Nikopol solar power plant.
The 200 MW plant was built in less than a year. In April 2018 DTEK signed an agreement for the design and construction of 200 MW solar power plant with Chinese company CMEC. The first solar panel on the SPP site was installed last October. The solar power plant was put into exploitation on January 2019.
The Nikopol SPP consists of 750 thousand PV panels located on the former quarry site.